Stamford Bridge Pumps Due Soon

As a result of my direct intervention I am delighted to announce that my manifesto policy for permanent pumps for Stamford Bridge will be actioned soon.

Stamford Bridge Mobile Pump

ERYC Statement

All Legal Agreements with the brewery are now in place

We have carried out a Habitat Regulation Assessment and submitted the report to Natural England, who have approved it.

We have completed and submitted all Environmental and Flood Risk Permits to the Environment Agency, who have acknowledged receipt and have not expressed any concerns.

Start date on site has provisionally been agreed with the Contractor for 27th February. Anticipated time on site is two weeks.

The pumps will not be operational immediately after we finish on site, we will need to wait for Northern Power Grid to connect the electric and Npower to fit the meter. We have raised orders to both, and are waiting for their programmes.

We have spoken to the landlord of the pub, and made him aware of our programme.