Stamford Bridge: Road Repairs Schedule Update

As numerous residents raised questions with me as to whether Roman Avenue pot holes could be repaired and/or the resurfacing moved forward I requested a schedule update from ERYC for Roman Avenue and also future works for Church Road.

ERYC Update

“Morning Cllr.

Sorry for the delay in replying, I’ve been waiting for info from other teams on the timescale for resurfacing.

We ordered for the worst potholes to be filled prior to the resurfacing as unfortunately it could not be advanced. They were completed on Monday this week. We’ll monitor the area leading up to resurfacing but hopefully we should be over the worst weather now!

Regarding Church Road, it’s currently ranked at no.340 on the unclassified roads list so any resurfacing work is at least 3 years away. Some localised work is proposed at the junction with the current resurfacing works, but nothing major.

Hope this helps, please feel free to call if any more clarification is required.”

Thank You ERYC

I believe this to be reasonable.

I would like to thank ERYC for saying it as it is.